Polished concrete vs. epoxy vs. urethane cement vs. MMA

The same 25,000 sf floor priced four ways over fifteen years — upfront cost, recoat cycles, maintenance and the hours the floor is out of service.

  • Upfront spread$2.50 → $14/sf
  • Downtime spread2 h → 5 days
  • Model area25,000 sf
  • Horizon15 years

Side-by-side

Engineering comparison

CriterionPolished concrete (800 grit)High-build epoxy (1/8 in.)Urethane cement (1/4 in.)MMA rapid-cure (2–4mm)
Installed $/sf$2.50–$4.00$6.00–$12.00$10.00–$13.00$8.00–$14.00
Expected life15–20+ yrs8–12 yrs15–20+ yrs10–20 yrs
Lifecycle work in 15 yrsRe-densify & re-burnish every 5 yrs (~$0.40/sf)1 full recoat in 15 yrsNone expectedTopcoat renewal ~yr 12 in heavy traffic
Install downtime / cure0–24 h3–5 days24–48 h2–4 h
Thermal shock tolerancen/a (bare slab)Poor above ~140°FExcellent, −40°F to +250°FGood, installs to −20°F
Acid / chemical resistancePoorGood (inorganic), poor (organic)Excellent incl. organic acidsGood
Moisture vapor riskBreathable — no MVBLimit ~75–80% RHTolerant, often 90%+ RHModerate, ~85% RH
Ideal facility fitDry distribution, high-bay pickingDry manufacturing, labs, corridorsWet food & beverage processingFreezers, 24/7 plants
CSI section03 35 4309 67 2309 67 2309 67 23
Estimate itOpen in estimatorOpen in estimatorOpen in estimatorOpen in estimator

Turnkey commercial ranges with standard preparation; moisture mitigation, cove and joints excluded so the systems compare like for like. How these ranges are built.

15-year TCO

What 25,000 sf costs to own

Mid-range installed price, plus recoat or renewal cycles at 70% of the original system cost (lighter prep, no MVB), plus routine maintenance per square foot per year. Downtime is not priced here because it depends on your throughput — but it is often the largest number.

15-year cost of ownership, 25,000 sf, mid-range pricing
Polished concrete (800 grit)$146,250
High-build epoxy (1/8 in.)$457,500
Urethane cement (1/4 in.)$325,000
MMA rapid-cure (2–4mm)$416,250

Initial installRecoats / renewalRoutine maintenance

SystemInitial installRecoats / renewalMaintenance (15 yrs)15-year totalPer sf per year
Polished concrete (800 grit)$81,250$20,000$45,000$146,250$0.39
High-build epoxy (1/8 in.)$225,000$157,500$75,000$457,500$1.22
Urethane cement (1/4 in.)$287,500$0$37,500$325,000$0.87
MMA rapid-cure (2–4mm)$275,000$96,250$45,000$416,250$1.11

Model assumptions match the Floor System Cost & TCO Estimator. How these ranges are built.

Reading the numbers

How the choice usually falls out

Dry warehouse, forklifts

Polished concrete wins on cost by a wide margin and never peels. Add ACI 302.1R polyurea joint fill. Use epoxy only for striped zones, battery rooms and maintenance bays where oil and acid land.

Wet process room, hot washdown

Urethane cement costs two to three times polished concrete upfront and still has the lowest risk-adjusted cost: epoxy embrittles under steam and organic acids, and a delaminated food-plant floor is a sanitation finding, not just a repair.

Freezer or 24/7 line

MMA is priced like urethane cement but returns the floor in hours. When a week of shutdown costs more than the floor, the downtime column decides it.