15-year lifecycle · downtime · exposure
Polished concrete vs. epoxy vs. urethane cement vs. MMA
The same 25,000 sf floor priced four ways over fifteen years — upfront cost, recoat cycles, maintenance and the hours the floor is out of service.
- Upfront spread$2.50 → $14/sf
- Downtime spread2 h → 5 days
- Model area25,000 sf
- Horizon15 years
Side-by-side
Engineering comparison
| Criterion | Polished concrete (800 grit) | High-build epoxy (1/8 in.) | Urethane cement (1/4 in.) | MMA rapid-cure (2–4mm) |
|---|---|---|---|---|
| Installed $/sf | $2.50–$4.00 | $6.00–$12.00 | $10.00–$13.00 | $8.00–$14.00 |
| Expected life | 15–20+ yrs | 8–12 yrs | 15–20+ yrs | 10–20 yrs |
| Lifecycle work in 15 yrs | Re-densify & re-burnish every 5 yrs (~$0.40/sf) | 1 full recoat in 15 yrs | None expected | Topcoat renewal ~yr 12 in heavy traffic |
| Install downtime / cure | 0–24 h | 3–5 days | 24–48 h | 2–4 h |
| Thermal shock tolerance | n/a (bare slab) | Poor above ~140°F | Excellent, −40°F to +250°F | Good, installs to −20°F |
| Acid / chemical resistance | Poor | Good (inorganic), poor (organic) | Excellent incl. organic acids | Good |
| Moisture vapor risk | Breathable — no MVB | Limit ~75–80% RH | Tolerant, often 90%+ RH | Moderate, ~85% RH |
| Ideal facility fit | Dry distribution, high-bay picking | Dry manufacturing, labs, corridors | Wet food & beverage processing | Freezers, 24/7 plants |
| CSI section | 03 35 43 | 09 67 23 | 09 67 23 | 09 67 23 |
| Estimate it | Open in estimator | Open in estimator | Open in estimator | Open in estimator |
Turnkey commercial ranges with standard preparation; moisture mitigation, cove and joints excluded so the systems compare like for like. How these ranges are built.
15-year TCO
What 25,000 sf costs to own
Mid-range installed price, plus recoat or renewal cycles at 70% of the original system cost (lighter prep, no MVB), plus routine maintenance per square foot per year. Downtime is not priced here because it depends on your throughput — but it is often the largest number.
Initial installRecoats / renewalRoutine maintenance
| System | Initial install | Recoats / renewal | Maintenance (15 yrs) | 15-year total | Per sf per year |
|---|---|---|---|---|---|
| Polished concrete (800 grit) | $81,250 | $20,000 | $45,000 | $146,250 | $0.39 |
| High-build epoxy (1/8 in.) | $225,000 | $157,500 | $75,000 | $457,500 | $1.22 |
| Urethane cement (1/4 in.) | $287,500 | $0 | $37,500 | $325,000 | $0.87 |
| MMA rapid-cure (2–4mm) | $275,000 | $96,250 | $45,000 | $416,250 | $1.11 |
Model assumptions match the Floor System Cost & TCO Estimator. How these ranges are built.
Reading the numbers
How the choice usually falls out
Dry warehouse, forklifts
Polished concrete wins on cost by a wide margin and never peels. Add ACI 302.1R polyurea joint fill. Use epoxy only for striped zones, battery rooms and maintenance bays where oil and acid land.
Wet process room, hot washdown
Urethane cement costs two to three times polished concrete upfront and still has the lowest risk-adjusted cost: epoxy embrittles under steam and organic acids, and a delaminated food-plant floor is a sanitation finding, not just a repair.
Freezer or 24/7 line
MMA is priced like urethane cement but returns the floor in hours. When a week of shutdown costs more than the floor, the downtime column decides it.